What procedures are involved when produce a self service kiosk

How to make a Self Service Kiosk and How long it will take?

When you placed an order to purchase self service kiosk, you will want to know the lead time for production, and may want to know what will the supplier to during the lead time.

Firstly the supplier, we, should collect all components from our suppliers, which takes usually 7 to 10 days. Because we need the real components to design the production drawing. Sometimes, the regular used components may no need to wait the real components to start drawing.

Secondly, making layout drawing according to real components or 3D, which takes about 3 to 5 days, and get your approval for layout.

Thirdly, making the production drawing after layout drawing finished, which takes 5 to 7 days.

Then, we start production for kiosk enclosure per below steps:

  1. Cut the metal sheets per the production drawing by CNC or Laser cutting machine.
  2. Bend the metal sheets and riveting rivets per the production drawing.
  3. Weld the small pieces together to form the enclosure per the production drawing.
  4. Sand the sharp angles and make all even.
  5. Clean the enclosure surface, like oil, dust.
  6. Paint the kiosk enclosure with required colors.

Quality checking for each step and altering if necessary.

The self service kiosk enclosure generally takes 15 to 20 days. If the production workshop is busy, the time will be a little prolonged.

After the kiosk enclosure finished, the next steps are assembly components and aging test, which usually takes 5 to 7 days depends on quantity for 1 unit of kiosk.

So for a self service kiosk, the average lead time is 35 to 40 days after PO issued.

We don’t suggest to rush for production, because rushing may rise the risky for poor quality or other problems.

Our sales representative will keep you are posted for the working status by sharing pictures or videos.

Shipment will be arranged after test finished, and after sales services are started.

Procedures for Making Metal Enclosure

Quality checking and altering after welding before surface treatment